More assistance / advise needed

Deys NassahMember for 20 years 5 months
Created
1
19
0
I may be working for a developer/client organisation working in mega projects in mid east. I am told that this type of organisation needs to plan in "funding" requirements to ensure that the money is available from sources like say the World bank or IMF etc...
This being the case, how and what would need to be shown on the schedule? Presumably this would be shown only at the higher level not the detailed level 3 or 4??

I would appreciate your views on the matter..

1 reply

Oldest first
  1. 0
    Pranab Kumar Deb ·
    dear Friend ,
    1. Funded projects need "Expected Cash Flow" presentation so that the funding agency knows when and how much money to arrange. I generated this at the end i.e. when i had the level 4 program resource loaded, if the project is just in planning stage and u have the total approximate estimated cost u can make the whole cost as a resource (load resource as three step distribution , not necessarily but i prefer it ) u can forecast expected cash flow.
    And yes u are making the strategic plan make it small and crisp with all majors works as a WBS Level.
    HTH
    Deb