Project Controls Manager interview questions needed

Mike MorrisonMember for 19 years 2 months
Created
67
17
0
What would be some good questions for interviewing a project controls manager:

We manage cost (prolog) and schedule (p6) for about $1Billion in University projects (about 300 projects from $100k to $100M).

67 replies

Oldest first
  1. 0
    Richard Spedding ·
    What are the early warning signs you look for when reviewing progress against the schedule, both on a project by project and at an enterprise level?
  2. 0
    Daniel Limson ·
    An ideal and appropriate question i have in mind would be:

    As a Project Controls Manager, What measures would you do or undertake to guarantee fulfillment of work schedule and complete the project within budget?
  3. 0
    Oliver Melling ·
    Good questions would be to ask them,

    ’How he/she would ensure that they provided the available project control resources to dispatch the tender and contract project requirements?’

    ’Whether or not they feel enterprise level planning software is required to meet the demands of modern day project driven organisations?’

    ’Do they believe a functional/weak/strong matrix management practice is better for controlling their project controllers, planners and estiamtors?’

    ’Do they prefer Back to the Future 1, 2 or 3?’
  4. 0
    Oliver Melling ·
    I’m moving to a new job at Oxford next week, but i have noticed that my profile has changed from Chesire to Merseyside?

    Don’t know why?
  5. 0
    Dieter Wambach ·
    I would sit him at a PC, open a real project in Primavera and let him evaluate this project. He would be informed, this is the test database and so no risk to destroy anything.
    By this I can see:
    - Aquainted to use Primavera
    - Which aspects are important for him
    - How is his strategy in unknown projects.
    - Does he realize strengths and weaknesses.
    It would be some discussion on those items --> How does he react - or she, of course.

    To Daniel:
    "guarantee fulfillment of work schedule and complete the project within budget". A candidate who would say so, would not be hired. CntrlsMgr has to indicate, were are deviations, risks and to show ways out of the dilemma, but he isn’t able to guarantee for the future.
    Regards
    Dieter
  6. 0
    Dieter Wambach ·
    Oliver

    GOOD LUCK!

    Dieter
  7. 0
    Daniel Limson ·
    Dieter,

    I think you have taken the question very literally, every body knows that nobody can predict the future, let me re-phrase it. I think the essence of the question is what will you do (measures you need to do)as a Project Controls Manager to complete the project on time and on budget.

    Cheers mate
    Daniel
  8. 0
    Oliver Melling ·
    Also, I don’t think it is neceassary for a planning manager to know how to plan on P5.

    A nice to have, but not a requirement.
  9. 0
    Oliver Melling ·
    Tis but a stones throw.
  10. 0
    Dieter Wambach ·
    Hi Daniel
    With this wording I agree. Sorry for misunderstanding - it’s the difference between native and foreign language.

    Hi Oliver
    In the company I work for, a Project Controls Manager has to create and maintain schedules. We have P3e/P6 as a mainline - with some projects in P3 and MSP due to customer’s wish as well. So P3e or P3 is a requirement and I test it.
    Regards
    Dieter
  11. 0
    Oliver Melling ·
    Dieter,

    What do the planners do if the planning manager is planning?

    Regards,

    Oliver
  12. 0
    Dieter Wambach ·
    Oliver
    It’s a question of title I assume. PCM is not necessary the Head of Department, but as his position is very important and is staffed with some power inside the project, we have this title.
    What should be the tool for project controls if not the schedule?
    Regards
    Dieter
  13. 0
    Christian Adrian De Vera ·
    Oliver

    I guess that is a pitfall of a Planning manager.. that he gets too much involved in creating schedules rather than managing his planners..

  14. 0
    R. Catalan ·
    It all boils down to what he knows about:
    1. Role of a PCM?
    2. His knowledge of Integrated Cost & Schedule Control
    3. Earned Value Analysis (as Clive has said)
    4. Problem solving approach
    5. Work attitude as part of a Team

    R. Catalan
  15. 0
    Oliver Melling ·
    Dieter,

    The schedule is the right tool for project controls, but the PCM should manage the workload and procedures that planners work to.

    The only thing a PCM needs to schedule is the workload of his team.

    Regards,

    Oliver
  16. 0
    Dieter Wambach ·
    Hi Oliver,
    the best basis for misunderstandings is no clear definitions of the terms. In the company I work for, a PCM among others creates and maintains schedules, and provides the required reporting inclusive performance measurement. In addition he may represent the PM and has a right for veto if there are not realistic scope of work, dates or budgets. This is quite powerful and requires some managerial behaviour. It’s much more than a scheduler, but he has to work with Primavera as well. It is not the team leader.
    In other companies it may be different.
    It depends on your team’s size and how it is staffed, if you only schedule the workload of your team or you have to work as a planner as well.
    Regards
    Dieter
  17. 0
    Carmen Arape ·
    Dieter,

    I understand your point BUT in your company the PCM is doing something wrong when he spends most of his time in scheduling.

    Sometimes the PCM creates so complicated way of scheduling and reporting that not ONLY the planners, BUT He waste all the time in feeding the schedule and processing.

    Where is the time for: analysis, assessing What-If scenarios and communicating the date forecast to the people that can take an action to change the future.

    OLIVER is trying to point out that PCM can not be all the time scheduling.

    Cheers
  18. 0
    Dieter Wambach ·
    Again, first its an item for definition second it depends on the size of project.If a project has a size that it requires more than one person for scheduling, he will more be team leader during project execution. We have some templates to be used as bricks, which makes life easier for the planner. As planning is easier in p5/P6 than in P3, this was another reason to switch.
    A PCM who has a "complicated way of scheduling and reporting" would work for a different company. With an effective way of working he will have plenty of time to perfom the total scope of work.
    Regards
    Dieter
  19. 0
    A D ·
    Dieter,

    I agree with what Oliver and carmen have written.

    the way u hav presented @ PCM, he sounds more like a Sr. Planner / Sr. Scheduler.

    His main job shud b to get d right things done (not by self) by others. He shud communicate with other departments to provide / show them where as a project, v r standing.

    He shud try to provide information which is more relevant to this specific project rather than using the traditional templates (bricks) alone.

    The crux of the matter is; he shud:
    - establish the standard APPROACH for the specific project to organise the various elements of the planning & project controls
    - He shud FACILITATE the planner / scheduler for formation of comprehensive time-phased budget by thorough schedule planning and cost estimating.
    - To control project activity flow by defining how work is formally authorised
    - To GUIDE planning team for making performance reports and SUGGEST ways to control changes to the project baseline.

    As far as project size is concerned, if the project size is bigger, then there will be PLANNING MANAGER ALONG WITH A PROJECT CONTROLS MANAGER.

    :-)
  20. 0
    Dieter Wambach ·
    Hi Raviraj
    I wrote "templates to be used as bricks". I didn’t write "using the traditional templates (bricks) alone". Projects are singular, it would be absolutely stupid to restrict a schedule to templates/bricks. It must be: bricks + individual. But there is no need for always reinvent wheels. This I meant by effectively working.
    You use a different definition than we do. That’s ok.
    Please show me an international law/regulation where this term is defined. There isn’t any. PMBoK: Nothing. Even in Germany where we have a industrial norm for everything, it isn’t defined. So we have to develop the term by ourselves, live with different definitions, and then discuss.
    Not all projects have a size of some billions of Euros or Dollars, that you need a team for project controls. Normal project life is different. Mostly one person will be ok (+replacement).
    Regards
    Dieter
  21. 0
    Oliver Melling ·
    And that one person will mostly be a planner who has been assigned the work by a PCM/Planning Manager.
  22. 0
    Dieter Wambach ·
    Hi Oliver, Raviraj
    This is no religious war. I explained how PCM is defined in the company I’m working for. My personal opinion doesn’t count. In other companies terms are used differently.
    I really don’t understand why you don’t accept. We all are working in projects most of us for changing customers and so we are accustomed (or should be ..) to adapt to different environments, to live with different cultures, with different terms. No need to fight and to evaluate, but to define and to discuss.
    By the way: If I would have to decide the terms, I would agree with Raviraj. I’ll try to modify the definition.
    Regards to all
    Dieter
  23. 0
    Oliver Melling ·
    Dieter,

    The whole point of the PMI BoK and the APM BoK is to make an internationally recognized lexicon for the project management industry.
    If your company bid upon a project of less than 100k that my or rav’s company were tendering and we saw that you had included a PCM, then it it possible that our companies would not choose your bid for contract award because it may look like your over estimating the planning requirements.

    This is a very simplistic example I know, but when do you work for say American clients (PMI) and you are a european company (APM), misconstrued information can cost money!

    Regards,

    Oliver
  24. 0
    Dieter Wambach ·
    Oliver
    I can’t remember that we quoted on such project of that size, so the risk you mentioned doesn’t fit. But I believe it is a good argument to reflect - thank you.
    Regards
    Dieter
  25. 0
    Dinesh Kumar Damavarapu ·
    Dear All,

    Project Controls Manager relatively a news position introduced on projects(in Asia, Middle East,UK and other part of the world).

    Traditionally, we used to have a contracts department who is responsible for all the cost and contracts related issues and a planner/scheduler who supports scheduling functions supporting project manager projects.Cost and scheduling interface used to be managed by the project manager. Due this reason, still there is no proper fortfolio for the project controls manager in the industry.I have worked on major projects and seen project controls manager mostly involved in the scheduling management role rather than project controls.

    Let us come to the basics, we all know what is project is; controls: To reduce or prevent the spread of,To adjust to a requirement; regulate etc.Project Controls Manager should be responsible for devising all the measures, implementing them monitoring them and controlling them, This is applicable for time, cost, quality and safety. Normally projects do have quality control and safety managers and these two item are left for them to handle which leaves cost and time to the PCM.Quantity surveying(including contracts) and scheduling departments should be part of Project Controls in order to be effective.

    Regards

    Dinesh Kumar
  26. 0
    Charleston-Joseph Orbe ·
    HI,

    Before you interveiw a candidate for Project Control Manager, you have to be praactical that not all written in the cv are correct.

    The best way to hire a prospective candidate is to undergo hands-on proficiency in Primavera P3.

    I have a lot of candidates for Junior Planning Manager but acting strange on the day of there schedule hands on proficiency exam in Primavera, Excel, Words, Access and Powerpoint.

    There alibi: I took a good offer only yesterday around 15,000 USD per month all inclusive.

    Anyone interested to work with me and undergo the process is most welcome. WE can arrange for online or virtual hands on proficiency exam, if interested. Just PM me.

    Cheers,

    Sensei
  27. 0
    Oliver Melling ·
    But what if they use MSP
  28. 0
    Charleston-Joseph Orbe ·
    MSP is nothing.

    There is not imagination in MSP.

    It is very easy to use that, in my standard, it is not really a planning tools.

    This is a big problem here in planning planet because anyone can use MSP and call themselves planner, even labourers from far away land can punch the keyboard of MSP and call themselves the greatest planners on earth or PP.

    Im sorry but this is only my humble opinion. IMHO.
  29. 0
    Charleston-Joseph Orbe ·
    MSP is nothing.

    There is not imagination in MSP.

    It is very easy to use that, in my standard, it is not really a planning tools.

    This is a big problem here in planning planet because anyone can use MSP and call themselves planner, even labourers from far away land can punch the keyboard of MSP and call themselves the greatest planners on earth or PP.

    Im sorry but this is only my humble opinion. IMHO.
  30. 0
    Oliver Melling ·
    Charlie,

    I think the point is that a PCM doesn’t need to be able to use planning software.

    Whether MSP of P3e, a PCM controls systems, processes and the planners who do the physical planning for him/her.

    IMHO
  31. 0
    Charleston-Joseph Orbe ·
    Hello Oliver,

    Your experience may gave you that conclusion.

    In my experience this is not the case. and if people work with my project control team, I have to ensure that my teams are proficient in the using planning software, Primavera P3.

    I dread hiring someone who claim in his cv that he know this and that, then at the end of the day I will find out that he dont know anything. Can you imagine the embarassment to the Client, executive management, etc.

    The worse thing to happen is to cover up the mess. AND THIS MEANS "I HAVE TO DO HIS WORK and he will sit and watch me do his work!!!!!! AHHHHHHHH what a shame!!!!

    Who’s head will roll??? I cannot afford to lose 20,0000 USD per mont all inclusive.

    This is only self preservation and to let people know I’m not gullible.

    Im sorry, my standard is to high.

    I will not hire housewife, wedding planers, smal time planners.

    They should be engineers who are professional planners.

    Cheers,

    Sensei
  32. 0
    Oliver Melling ·
    Charlie,

    What company is paying $240,000 per annum for a planner?

    Oliver
  33. 0
    Charleston-Joseph Orbe ·
    Oliver,

    Secret

    You should know how the world revolve.

    People will know the company, they will present themselves and ask for smaller packet.

    some planners go lowest, 3,000 AED per month. it will not be surprising if 1 million applicant, housewife, labourers, illegal immigrants, etc. will present themselves with bogus credetial not authenticated by independent third party

    Competition is very tough if you are in this level. One mistake, bye bye, no comapssion.

    To survive, you are simply the best.

    Cheers,

    Sensei


  34. 0
    Oliver Melling ·
    Yes,

    But what company is paying $240,000 per annum?
  35. 0
    Charleston-Joseph Orbe ·
    Hi Oliver,

    That is not the point of this thread.

    If you are really interested to know, please start a thread regarding paychecks of planners. As for me I’m not interested to what other people earn.

    So please follow my advice if you are sincere in your quest to know how much company are paying there planner.

    IMHO, mine is still a secret which I believe majority of our member also wanted that to keep secret how much there company are paying them.

    Cheers,

    Sensei
  36. 0
    Charleston-Joseph Orbe ·
    And going back to the thread?????

    Actually my question is very fair.

    It is like this.

    Base on your experience, please prepare a new hypothetical project (Villa Construciton, Residential Building Construction, Tower/High Rise Construction, Bridge Construction, Industrial Construction, Oil and Gas Facilties, etc.)

    Limit the activities from 15 to 30 activities. The activity type should included task, milestiones and hammock.

    Please demonstrate proficiency in export/import command
    Please demonstrate proficiency in global change.
    Please demonstrate assigning resources and cost.
    Please demonstrate WBS and Activity Codes.

    From the new project, please produce a Progress S-curve in Excel chart.

    Please prepare a Narrative of your program and Progress S-curve.

    What is planning?
    What is Project Control?

    Demonstrate expertise in system approach in Project Planning and Project Contorl.

    I believe this is a fair requirement to a Prospective "PROJECT CONTROL MANAGER" candidate for employement
  37. 0
    Charleston-Joseph Orbe ·
    Believe me,

    If any planner can demostrate the above during interview, WHEWWwww,

    Your price is sky is the limit.

    The company will beg for your to join them.

    Based on my experience.

  38. 0
    Charleston-Joseph Orbe ·
    But what happen during interview:

    Some prospective candidates chicken, they are scared to show what they know about planning, so the best alibi, i got a good offer yesterday only (liar).

    Some candidate bring their laptops, recent reports showing P3 schedule, S-Curve,, BUT BUT, when the proficiency hands on demonstration: The laptop got password which the candidates dont know the password. OK company will lend the company laptop, but when candidate used, candidate destroy the company laptop. NO exam possible

    In conclusion: People acting funny when they say more than in their cv. That is why hands on proficiency is very important.

    Cheers,

    Sensei
  39. 0
    Anoon Iimos ·
    Charlie,

    Have you seen or used P6 by any chance? If you did, can you share some comments about it?...please...?
  40. 0
    Dinesh Kumar Damavarapu ·
    Hi Charleston,

    There are many project controls/plannning engineers who can do far better than quite many project controls managers in UAE but their CVs may not reflect all that.Even their CVs do reflect but there are many other factors that are affecting them becoming project controls managers.

    For your information, P3,P5 now P6 are just tools only to allow you to make scheduling but not planning.If one do not know how to use P6 or P5,then the same can be leart in no time, but basically planning engineer/planning manager/ project controls manager should know how to plan.He/she should know the time required for individual tasks, the sequence of work, cycle time analysis,cost engineering and so on. Beside all these requirement he should also know project management which would allow him to work with project management team closely and effeciently.He also should know contracts and it relation to the schedule and delay analysis etc.

    Regards

    Dinesh

  41. 0
    Charleston-Joseph Orbe ·
    HI Dinesh,

    I agree with you.

    It so happen that I come across only with P5. Some friend of mine ask me to do Planning/scheduling using P6. I learn only the basic since I have to present a schedule in one week time. I did finish the fundamentals using P6.

    After that..... no more. The point here is to know that fundamental in such a way that whatever software available, we can always present a plan.

    Using MSP is never a problem to me, whatever version or upgrade.

    The project environment Im in at the moment is not using P5. So, I got stuck with P3.

    Generally, Project Control is trackcing. It is piece of cake. The basic problem also is that the line manager and top manager dont want to listen?????

    Cheers,

    Sensei
  42. 0
    Charleston-Joseph Orbe ·
    Anoon,

    I did use P5.

    But only the fundamentals in such a way that I can prepare a resource and cost loaded schedule.

    I master it in one week time.

    The intricacy of P5, I was not able to grasp since I only have to prepare a resource and cost loaded schedule using P5. No update.

    I have the software. This was the payment I request for the services I provided.

    But the work environment I’m in is not using P5, so any skill I derive using P5 is useless.

    Cheers,

    Sensei
  43. 0
    Anoon Iimos ·
    really?...somebody gave you P5 (software) as payment for your services?...but you haven’t seen P6 yet?..you’re a very lucky man Charlie
  44. 0
    Sudharsan V ·
    PCS Manager (Project Controls Manager) : Role will vary according to the Project & Organization he is working for. PCS (from Project Management firm) and PCS (from Contractor) will have slightly different role.

    PCS Manager will have the following dept. reporting / Supporting to him

    1. Planning
    2. Cost
    3. Document Control
    4. IT (can support them for tools & tech implementation)
    5. Contracts Department

    PCS should be aware of tools and technology BUT not mandatory to have in depth knowledge of products viz, P6

    Softwares are tools only, it can’t be learnt over a period of time but not the PLANNING.

    PCS Manager should have the vision on How to execute the Project within specified TIME & COST.

    1. He should Develop the WBS (not P3 WBS) on overall Project
    2. He should be able to write the following procedures

    . Planning Procedure (including software to be used, activity duration shuld not exceed 15 days, how to updatge progress, how to give activity id, how to measure performance, reports to be prepared on regular intervals, what if analysis etc)

    . Document Coding Procedure - How to number each document viz, Submittals, Shop Drawings, Other Drawings, RFI, MOM etc

    . Develop Cost Coding Procedure - This will help to identify the cost of the project at various levels (not to confuse with cost of P3). How to use Expedition / Prolog / Excel or some other programme to develop cost worksheet.

    . Develop Risk Management procedure

    . Should Co-ordinate to develop PMP (Project Management Plan) or Project Execution Plan (PEP)

    . Always Proactive to bring notice about the kind of risks, deviation etc in the Project

    Like this he should be abel visualise and should create a good interface of Planning, Costing & Document Dept.

    For a big Projects / Programme various dept Planning Engineers / Managers will be reporting to PCS Manager / Director.

    In short PCS Manager should be well versed Planning, Costing & Document Management. He should create a common interface between all of them.

    Due to lack of time, I could not write more detail role of PCS.

    Bye

    Sudharsan



  45. 0
    Charleston-Joseph Orbe ·
    Hi Sudharsan,

    You mean to check and ask your Project Control Manager if he knows what your are trying to tell here in PP.

    Please let us know.



  46. 0
    Sudharsan V ·
    Hi,

    These are the responsibilties in a big project environment for a PCS Manager. So you can ask questions to him according to your requirement / expectations from the PCS. (First you should specify the role and responsiblities of PCS Manager and obviously checking his/her skill relevant to the expectations will be easy)

    But definetly not checking too much knowledge of Primavera skills as somebody mentioned here.

    In depth knowledge is always a plus

    Regards,

    Sudharsan
  47. 0
    Adedeji Adelaja ·
    To effectively monitor/control, you need a good understanding of the variables (people, project and tools to be used)involved in the process being controlled.

    IMHO, I lean towards Charles’s definition.
  48. 0
    Andrew Tan ·
    Hi,
    IMO, Asked
    1. What do you propose the scope of PCM should be. (reversal question)
    2. If you are in the oil/petro(I am in this), asked the various discplines and problems that lies in each discpline.
    3. For specifics one, asked for hands-on demo of 1 discpline in either E / P / C. The PCM should be able to draft out.
    4. Asked what analysis system to deploy for control - planning and cost
    5. How to reduce risk and provides effective control.
    6. Efficiency with the various tool required.
    7. The projects that is involved.

    Have to know how to single out participation and causation, ie are u the reason for success of project or just a participant.

    For qn.2, I manage to generate a general template for EP of all the discplines which goes into my head. :>
  49. 0
    Oliver Melling ·
    Adedji,

    Charles’ opinion was that a PCM should be able to use P3.

    In a company where you are a PCM, such as a defence company, you may have 100 schedulers working for you across 20 different business units.
    You may also have 4 or 5 different planning software packages, MSP, Primavera, PowerProject etc.

    So, the point being made is that knowledge of how to use the software isn’t important to a PCM.
    He/she just needs to know it can deliver the required level of project data to the PM’s and PE’s in the business.
  50. 0
    Chris Oggham ·
    Oliver,

    I agree with you 100%. It might be argued that the PCM should have some familiarity with using the different software packages, but I don’t think it is essential. As long as they know what is wanted and how this can be best delivered, this should be enough.

    Chris Oggham