MEP Installation Sequence

Shaiju ThomasMember for 20 years 6 months
Created
2
3
0
Hai Friends,

Is there is any typical (traditional) installation sequence (priorities) between MEP systems such as AC ducts, Chilled water piping, Firefighting piping, Plumbing & Drainage piping, Electrical raceways etc, when all this work would come in one area.

2 replies

Oldest first
  1. 0
    Andrew Pearce ·
    Generally there is not a typical sequence because all installations are different. You need to look at the drawings, particularly any sections. Think what is highest, install that first, think what is most flexible, install taht last.
    You may find that in most cases Duct and any form of pipework is installed prior to electrical works.
  2. 0
    Shaiju Thomas ·
    Thanks Andrew, I agree. We have to look into the combined services drawings, sections. But it is difficult to show this things while developing a program.