materials on site

Sinan FahmiMember for 19 years 10 months
Created
6
4
0
Dear all,
i received a material on site (lift) before one month and we get approval from the clinet to get 60% from the it cost, now shall i reflect to the activity of lift work by the way this activity should start after three months

6 replies

Oldest first
  1. 0
    Raja Izat Raja Ibrahim ·
    Sinan
    it is depends to the sequence of construction, is there is an access and it shoudlnt be impact to other works
  2. 0
    A D ·
    Absolutely sinan,

    If material has arrived at site, you shud reflect it in the program and intimate to client.

    You can claim for that amount as well. Just think, if you are finishing project before time, then client should pay the required amount. Hope the logic fits here!!

    Cheers,

    Raviraj
  3. 0
    Ashraf Jahangeer ·
    Hi there,

    Although the physical progress for material delivery can be taken when it is delivered and accepted by client.

    The invoicing will depend on the Cost element of this material so if it is not a seperate entity as a material element and is part of Construction you cannot bill it when it is used up during construction.

    I think this is the case for Sinan. So it is good for him that his clinet has agreed for 60 % progerss which he can invoice now. The rest he can bill when it is used up in Construction.

    Regards,

    Ashraf
  4. 0
    Sinan Fahmi ·
    YES AHMED YOU ARE RIGHT, ACTUALY WE GET 60% FOR THIS ITEM AND WE DIDN’T START THIS ACTIVIY TILL NOW JUST WE DELIVERD THE MATERIAL, SO I THINK I HAVE TO REFLECT IT IN THE PROGRESS AND THE REAMAING 40% WILL BE IN THE CONSTRUCTION AND COMMISSION
  5. 0
    Ashraf Alawady ·
    for the WBS and the proper sequace of the activities we have to include in the base line progamme the following;-

    Separete activity for Materials Submittals.
    Separete activity for Materials approvals.
    Separete activity for Materials procurement.
    Separete activity for Materials deleverd to site.

    and all the above with the approvals of the shop drawings shoud be the predessors for the starting of any physical activites of the site works.

    Thanks


  6. 0
    Ishmael Mutsvanemoto ·

    All, Following on from your

    All,
    Following on from your previous email on this forum about bulk material, I am interested in picking your brains on the experience gained since. I am interested in tracking and reporting BOQ/BOM in P6 per WBS or other means in Primavera once the material is on site during construction. I would appreciate your help and if possible please send me a sample WBS to ishmael.mutsvanemoto@btinternet.com.

    Thanking your in advance.

    Regards

    Ishmael
    0082-10-8687-9498

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?