criteria for Progress evaluating

Aqil MahmoodMember for 21 years 1 month
Created
5
2
0
hi.. for individual activities it is very clear to update them based on quantities consumed , however what do u suggest is the most accurate method for evaluating total percent progress of the project (Actual Vs Planned) and why.
More over in projects where we have huge use of equipments (Earth works), is it possible to show the total percent completion of the project in terms of equipments?



5 replies

Oldest first
  1. 0
    Shaiju Thomas ·
    I suggest to convert the quantities (of different materials and equipments) into a common term such as manpower or effort.This can give a realistic overall progress picture.
  2. 0
    Aqil Mahmood ·
    shiju u r reply is appreciated... but hw it is possible to convert equipments usage into mandays (this would b assumed only)...
  3. 0
    Zhang Haixiang ·
    Hi,
    i think using equipments usage is not the best way,May be the production is better,e.g. rock have been excavated...

  4. 0
    Dattatreya Padharthi ·
    Any work executed by an Equipment whether its a welding Machine or an excavator can be converted into Man-hours/Efforts. It all boils down to the type of Contract (Engineering/LSTK/Construction or others)the progress Measurement System. When to talk about X thousand Construcion Manhours ona Project, it means real Construction efforts & not the equipment hiring/buying costs associated with it.

    Cheers
    Dattatreya
  5. 0
    Armando Moriles ·
    Hi...I find this topic interesting and I seemed to agree with Dattatreya. I once joined a project wherein included in the contract was what they called a Unit Price Anaylysis (UPA). In the UPA for example common excavation, it stipulates the equipment hours and manhours per m3. But, the number of equipments at site was equated only to a portion of the contract which was the mobilization.The engineer could say whether the contractor is under mobilization or not. If the production is low, the engineer after further substantiation could say to the contractor that it is because you are under mobilization, a breach of contract or the effeciency of equipments are low. The production required could be theoritically calculated and the equipments could operate on extended working hours.

    Regards,

    Arman


Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?