Total float
In the Open Standard
Dante ManitoMember for 19 years 8 months
- Created
- 10
- 2
0
Can anybody here help me fix my problem? My problem maybe is quiet simple for more experience planners. Just recently i develop a level 3 schedule for a petrochemical project a newly awarded project to our company.The project start will commence on July 15 2007 and mechanical completion on March 8 2009 as per milestone submmited by the client.But when i finished develop the schedule my project manager give me instruction to change the start date to September 15 2007.Here comes my problem - When i change the start date some activity bar color turns to red and create a negative total float as high as -51.How can i fix this problem?
10 replies
Oldest firstLog in or join to reply