Updating the program

A DMember for 19 years 5 months
Created
53
6
0
Hi Guys,

One of the clauses of contract says "The network shall be updated monthly for actual progress and MINOR CHANGES IN ACTIVITY DURATIONS TO REFLECT CURRENT INFORMATION AND SUBMITTED TO THE EMPLOYER REPRESENTATIVE. All Logic and duration changes shall be reviewed with the Employer Representatives Assistant."

Even it is written in the contract, r v supposed to make these changes in the updated program?

Is there any documentation (Any Book) to support this?

I had made recovery programs, accelerated programs, further revisions and stuff like this, but never ever done these change in durations and logic directly.

Any suggestions please?????????

Cheers,

Ravi

53 replies

Oldest first
  1. 0
    R. Catalan ·
    Hi Raph

    Your paper is of great interest to me. Pls send me a copy rrcatalan@hotmail.com

    Thanks a lot.

    Cheers
  2. 0
    Mohamed ibrahim ·

    Hello Guys,I have a small

    Hello Guys,

    I have a small question on MSP, How to reschedule and update the project to come out with Finish Variance?

    I'm seeking your help

     

    Best Regards 

    M.I

  3. 0
    Zoltan Palffy ·

    Yes make the changes in the

    Yes make the changes in the updated program?  But run a claim digegr report and or create a narrative telling them what changes you have made. List activities added ro deleted, List chnages to original durations and list any logic changes.

    Is there any documentation (Any Book) to support this? yes this is in the contratc it says to tell then what you chnaged I have listed what you should do above

    I had made recovery programs, accelerated programs, further revisions and stuff like this, but never ever done these change in durations and logic directly.

    Impossible if you made a revcovery or accelerated program then you MUST have either changed the durations (Shorter) or made logic changes by doing things concurrently is relationship chages from FS to SS (with a lag)

Log in or join to reply