Why P3 Calculate backwards?
In the Open Standard
Angel CruzMember for 16 years 5 months
- Created
- 6
- 3
0
I encounter some difficulties on my P3 Schedule. P3 calculates backward in some of my the activities. On my Project Overview : Project start on 08FEB10 and Project must finish on 17AUG13.
For example I have an activity having duration of 10 days without any predecessor and succesor. So, P3 usually gives ES 08FEB10 EF 17FEB10, but on my file P3 gives ES 08AUG13 EF 17AUG13.
Is there any problems with my setting?
Why P3 calculate backwards?
How to correct this kind of activities?
Tnx.
Angel
For example I have an activity having duration of 10 days without any predecessor and succesor. So, P3 usually gives ES 08FEB10 EF 17FEB10, but on my file P3 gives ES 08AUG13 EF 17AUG13.
Is there any problems with my setting?
Why P3 calculate backwards?
How to correct this kind of activities?
Tnx.
Angel
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?