Date scheduling issue
In the Open Standard
Manfredo JustinianoMember for 18 years 11 months
- Created
- 2
- 4
0
Hi:
Could some one help me to understand this figure?:
Im using P5. I have 2 schedule one I used as a primary base line and the other as the current project, when I export to excell file the fields:
Star, Finish, BL1 Start, BL1 Finish,
some dates from original single file (before assining as a base line) of both files had been modified?
What I have on my mind is to compare both, but it both change, and there is not a static baseline there is not way to do it.
Thanks,
Manfredo
Could some one help me to understand this figure?:
Im using P5. I have 2 schedule one I used as a primary base line and the other as the current project, when I export to excell file the fields:
Star, Finish, BL1 Start, BL1 Finish,
some dates from original single file (before assining as a base line) of both files had been modified?
What I have on my mind is to compare both, but it both change, and there is not a static baseline there is not way to do it.
Thanks,
Manfredo
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?