Date scheduling issue

Manfredo JustinianoMember for 18 years 11 months
Created
2
4
0
Hi:

Could some one help me to understand this figure?:

Im using P5. I have 2 schedule one I used as a primary base line and the other as the current project, when I export to excell file the fields:
Star, Finish, BL1 Start, BL1 Finish,

some dates from original single file (before assining as a base line) of both files had been modified?
What I have on my mind is to compare both, but it both change, and there is not a static baseline there is not way to do it.

Thanks,

Manfredo

2 replies

Oldest first
  1. 0
    Cyril Armentia ·
    Hi,

    You are confused between ’Primary Baseline’ and ’Original’ baseline.

    Possibly that you haven’t created your ’Original’ baseline yet or maybe you have not assigned your ’Original’ baseline into the primary baseline window.

    If the primary baseline is ’current project’ dates for your baseline will also change when you change your schedule.

    Check your primary baseline window. It must have the assignment of your ’original’ baseline.

    Cheers,
  2. 0
    Akhilesh Shukla, CCE EVP PMP ·
    Dear Manfred,

    Please ensure that you have saved your baseline schedule in peoper way i.e. assigning it (the schedule U want to keep as basline) as primiry baseline.

    The symptoms as U mentioned are frequent when baseline is not saved.

    Regards

    Akhilesh