MS-Project

Rajesh AnandMember for 19 years 10 months
Created
2
2
0
Hello to all Planners

I have a doubt when I insert resources to the activities, why does the duration changes. Please clarify it.

regards

rajesh

2 replies

Oldest first
  1. 0
    J Venkatesh PMP PSP ACIArb ·
    when u r entering resource , try by disabling Effort driven option, and also t depends upon the type u r choosing either Fixed time / Fixed units ....

    Venkat
  2. 0
    Tommy Nug ·
    You can also go to Tool/Option, and disable effort driven option to change the property every time you create a new activity.