MS-Project
In the Open Standard
Rajesh AnandMember for 19 years 10 months
- Created
- 0
- 3
0
Dear Sir,
Thanks a lot for answering my question. Now I have a peculiar question, I want to know how to give calendar as it is given project standard calendar. It is set from Year 1984 to year 2049, everything set as same non default working time. I want to know how & why? Please explain me sir.
With Regards,
Rajesh
Thanks a lot for answering my question. Now I have a peculiar question, I want to know how to give calendar as it is given project standard calendar. It is set from Year 1984 to year 2049, everything set as same non default working time. I want to know how & why? Please explain me sir.
With Regards,
Rajesh
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?