Hi:
I am using P5 and I got two Projects:
Project A: Engineering & Procurement
and Project B: Construction & Commissioning
I want to merge both into Project A. The particular matter is that Both Projects are linked (have relationships between activities). So I want to keep the links. I had tried by copying and paste WBS (Project – WBS), but some links from Project A keep pointing Project B.
Is it possible to do it automatically or I have to fix it manually? I am talking about 10000 activities’ project.
Or maybe there is another way of merging it?
Regards,
Manfredo.
I am using P5 and I got two Projects:
Project A: Engineering & Procurement
and Project B: Construction & Commissioning
I want to merge both into Project A. The particular matter is that Both Projects are linked (have relationships between activities). So I want to keep the links. I had tried by copying and paste WBS (Project – WBS), but some links from Project A keep pointing Project B.
Is it possible to do it automatically or I have to fix it manually? I am talking about 10000 activities’ project.
Or maybe there is another way of merging it?
Regards,
Manfredo.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?