Numerous Amount of Positive Float
In the Open Standard
Leonard MonMember for 19 years
- Created
- 3
- 2
0
Hi To All,
I need your valuable input regarding the below:
A particular activity (finish of survey work) in the Baseline CPM-PS has an EF on 21 Nov. 2007 with a total float of 42. However, in the Updated Current CPM-PS, such activity appears to have an EF on 21 feb. 2008 with a total float of 840 days.
I suspect that the updated Current CPM-PS portrays an unrealistic amount of Positive Float.
Is there something wrong about it? Kindly advise me how to make the necesary adjustment or to correct it.
Pls. note that we are using P3 Primavera.
Your reply is highly appreciated.
Best regards.
leonard
I need your valuable input regarding the below:
A particular activity (finish of survey work) in the Baseline CPM-PS has an EF on 21 Nov. 2007 with a total float of 42. However, in the Updated Current CPM-PS, such activity appears to have an EF on 21 feb. 2008 with a total float of 840 days.
I suspect that the updated Current CPM-PS portrays an unrealistic amount of Positive Float.
Is there something wrong about it? Kindly advise me how to make the necesary adjustment or to correct it.
Pls. note that we are using P3 Primavera.
Your reply is highly appreciated.
Best regards.
leonard
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?