NUMEROUS ADDITION OF WORK TO BASELINE PROGRAM

Mohamed YusufMember for 13 years 6 months
Created
3
2
0

Hi, I have been working in a Project with duration of 9months, supposed to complete by Sep'13. Due to various alterations in the Finishing Schedule and Nomination of new works, the project has been dragged till date, with every day addition of new works.

Now, the Management has asked us to submit an impacted program for depicting delay incurred, basically for claim.

Kindly advise, what should be the approach as the baseline program has nearly lost its orginality due to numerous changes.

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi MohamedWelcome to Planning

    Hi Mohamed

    Welcome to Planning Planet

    Step 1 Save the original (not progressed) baseline as a new file called Extra Work.

    Step 2 Add the new work as individual tasks and arrange the logic.

    Step 3 Reschedule - This will give you the revised completion date and EoT entitlement

    Step 4 Add the original progress - this will provide a Time Impact Analysis for cost and concurrency.

    Best regards

    Mike Testro

  2. 0
    Gary Whitehead ·

    If the client is adding new

    If the client is adding new scope daily, after the contractual completion date, is time not at large?

  3. 0
    Mike Testro ·

    Hi GaryTime is not at large

    Hi Gary

    Time is not at large if there is a contractual mechanism to award an EoT for extra work ordered by the client AND the client abides by it.

    Best regards

    Mike Testro