Quantities for tender programme

Rubas M. KuttyMember for 18 years 11 months
Created
3
2
0
While constructing a tender programme, the item quantities are sourced either from BOQ or detail drawings.

While the former is a ready reference and the latter may consume time, which one do you prefer?

3 replies

Oldest first
  1. 0
    Anoon Iimos ·
    you are lucky if you got BOQ and detailed drawings during the Tender Stage,

    for me there’s no preffered reference, i suggest you gather as much information that you can
  2. 0
    Johny Kesserwany ·
    By lack of time go by BOQ quantities for the tender! If you get the project you’ll adjust the quantities if needed...

    JK
  3. 0
    Abhijit Kale ·

    Generally during tender there are no detail drawings available, so we have to go for BOQ given by the client.

    In case if detail drawings are availabe you can cross check the quantities for the accuracy in your estimated price.
    Cheers,
    Abhi