baseline update progress

Lorenzo TolentinoMember for 19 years 5 months
Created
5
2
0
Greetings!

pls give me some idea why is it whenever i update progress, CTRL+F9, my baseline schedule i get negative floats on some activities? i supposed it shouldn’t be that way since this is an update progress of the baseline schedule and not updating the current sched...kindly give me some idea on this matter...what causes the negative floats of the above? thanks a lot and i wud aprc8 much ur help!!!

5 replies

Oldest first
  1. 0
    Anoon Iimos ·
    i don’t understand why you’re doing it, in principle, you don’t have to update the Baseline, you update only the current schedule.

    in updating baseline in order to get the planned progress, you don’t have to change anything, you update it perfectly as planned.
  2. 0
    Lorenzo Tolentino ·
    thank you mr. anoon for your reply...however, how do i get the the planned progress of every activity for a certain period of time? what we usually do here is that i make a copy of the baseline schedule then i would run that copy, CTRL+F9, to get the planned progress...is there a better way? Tnx a lot...
  3. 0
    Anoon Iimos ·
    you don’t have to make multiple copies of the baseline, i suggest you study what a Data Date is...
  4. 0
    Armando Moriles ·
    Lorenzo,

    Try to check if you have constraints applied on those activities that generate negative floats...

    With regards to baseline updating, I agree with Anoon...

    Regards,

    Arman
  5. 0
    A D ·
    Or otherwise, there must be an imposed finish date for the project. (MUST FINISH BY)

    This will generate negative float. Check this too..