Curves Early and Late in P6
In the Open Standard
Felipe N GMember for 18 years 6 months
- Created
- 6
- 2
0
Hello,
In P6 to see the early and late curves i choose Resource Usage profile and on Display with right click i choose Resource Usage Profile Options and click remaining early and remaining late in the column cumulative.
how can i obtain the values of this curves in P6? Which reports can i use? or is there other way?
Thank All
Regards,
Felipe
In P6 to see the early and late curves i choose Resource Usage profile and on Display with right click i choose Resource Usage Profile Options and click remaining early and remaining late in the column cumulative.
how can i obtain the values of this curves in P6? Which reports can i use? or is there other way?
Thank All
Regards,
Felipe
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?