S- curves

Moutassem Al KouatliMember for 19 years 1 month
Created
25
6
0
Dear planners,

i am just looking for some information, regarding S-curves,
definition, preparation methodes, analysing.
if somone has a paper or reference or a link, i would be very thankfull.

cheers.

Regards

25 replies

Oldest first
  1. 0
    Mohammed Mujtaba ·
    Dear Moutassem ,
    The S-Curves are the curves which represents the planned progress and actual progress. The values can be derived from the primavera itself. If you need the detail information send me a reply to mdmujtaba24@gmail.com.
    I will send it ...Inshallah
  2. 0
    K Z ·
    Hello Mohammed,
    I will be very grateful if you can send me detailed information about s-curve. My email address is kemezuofa@gmail.com.
    I will be very grateful if you can help me.
    Regards.
    Keme
  3. 0
    Ashish Jn ·
    Dear Mr mohammed,

    can u plz forward the same to me also at ashish_jain100@yahoo.com.

    Thanking u in advance

    Regards,
  4. 0
    Mohammed Mujtaba ·
    Dear All,
    The S-Curves are prepared based upon manhours.
    In primavera P3, Go to Tools, then Tabular Reports, then Resources, then Loading.
    Click on Loading. Click on add (it will open one box).
    Then Go to Modify Tab and select your resources.
    Then in Format Tab select Export report in CSV format and browse the location where u want the file to be saved.
    Then in the same tab you can select the activity code.
    Then in the Timescale tab you can select the data range (ie..the range of dates u want the s-curves values)
    Then in the same in the display box u can select the typr ie wekkly ,monthly (If u select weekly it will display the values in week).
    Then click OK and RUN.
    It will display the excel file (If the file is not displayed at that time go to the specified location which u have given and open it)


  5. 0
    Christopher Nicolas ·
    A silly question I know but I can’t figure out how to produce an S Curve in P6 - I know how to in P3 but can’t figure it out in P6 - help please.......
  6. 0
    K Z ·
    don’t know how to produce on p5
  7. 0
    Arnold Puy ·
    Hi Christopher,

    Send me your email address and I’ll show how to do it. I will send to your e-mail the snapshot in P6.

    HTH.

    Arnold
  8. 0
    K Z ·
    Arnold please can you send it to my email too.
    it is kemezuofa@gmail.com
    Thanks in advance
  9. 0
    Arnold Puy ·
    Hi,

    I sent it already.

    HTH.

    Arnold
  10. 0
    K Z ·
    Arnold,
    Could not find it.
    Please could you send it again.Kemezuofa@gmail.com or kemezuofa@yahoo.com
    I do appreciate.
    Regards,
    Keme
  11. 0
    Mertz Balanon ·
    Hi Arnold think this is my second request I really dont know how to prepare S-curve in P5 please can you help me.. my email is mcbalanon@hotmail.com
  12. 0
    Arnold Puy ·
    Guys,

    Already sent.


  13. 0
    Mertz Balanon ·
    Hi Arnold tnx again got the guide in producing S-curve. as you know im new in P5 i just came because the guy who used to prepared the programme resigned so i have to assume. my other problem is the resources is loaded in days calculstion now the new Planning engr of Consultant is asking me to prepare the weight % in manhours. whats the fastest way to do it? in P5? i cant imagine 9K+ activities to be loaded in manhors.

    Salamat...
  14. 0
    Ferdinand U. ·
    hi try global change or excel import, multiply by 8.5 to 10 hrs per day
  15. 0
    Arnold Puy ·
    Hi Mamerto,

    What type of Resources? Labor or Nonlabor? If you are talking about Manhours, this is Labor. If your Resources loaded in days, just multipy it by 8 hrs or 10 hrs per day depending on your calendar’s assignment.

    Mamerto, I can do it for you. Pls. send me your .xer file to p3-fer@sixco.ae

    Arnold
  16. 0
    Arnold Puy ·

    You can use the Resourge Usage Profile, Resource Usage Spreadsheet --> spreadsheet option --> Calculate Average.



  17. 0
    Wilson Ho ·
    Hi Arnold,

    Pls send me the info to wilsonho188@gmail.com.

    Many thanks.
  18. 0
    Arnold Puy ·
    Hi Wilson

    Already sent.

  19. 0
    Sajid Balma ·
    Hi Arnold
    Will you please send it to me too on aliali@cyber.net.pk?

    I will be really grateful.

    Thanks & Regards
  20. 0
    Arnold Puy ·
    Hi Sajid,

    Already sent.

  21. 0
    Mohamed Edris ·
    Hi Arlond,

    Would u plz send it to medris_cii@link.net
  22. 0
    Arnold Puy ·

    Already sent.

  23. 0
    Arnold Puy ·

    Already sent.

  24. 0
    Marcus Love ·

    Hi ArnoldWill you please send

    Hi Arnold
    Will you please send it to me too on marcus.love@live.com.

     

    It would be highly appreciated!

    Thank you very much and have a great weekend.

    M.Love

  25. 0
    Rafael Davila ·

    AFTER SETTING YOUR TEMPLATES

    AFTER SETTING YOUR TEMPLATES EARLY AND LATE CURVES FOR YOUR SCHEDULE AND THE BASELINE SHALL BE JUST A FEW CLICKS AWAY.

    http://www.youtube.com/watch?v=WkWizInifAU