To progress or not progress
In the Open Standard
Stuart AtkinsonMember for 22 years 9 months
- Created
- 9
- 2
0
I am currently working for a contractor as the ’contract planner’. The form of contract is ECC 2nd, Option C.
When assessing a compensation event the Client says we should update the accepted up to the time of the event, and then input the event to evaluate its effects.
Does the planning community agree or disagree with this approach?
Or is the last accepted programme used without progress inputted?
I would appreciate input from either Client or Contractor organisations.
Thanks,
Stuart
When assessing a compensation event the Client says we should update the accepted up to the time of the event, and then input the event to evaluate its effects.
Does the planning community agree or disagree with this approach?
Or is the last accepted programme used without progress inputted?
I would appreciate input from either Client or Contractor organisations.
Thanks,
Stuart
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?