Activity label in P6

Nithin ShettyMember for 22 years 1 month
Created
2
4
0
Can anyone please help me to know how to hide activity label in the time scale display in P6.

Thanks in advance.

2 replies

Oldest first
  1. 0
    Izam Zakaria ·
    Same as P3...just remove the label on label tabs
  2. 0
    Chee Sean Moo ·
    Hi,

    Menu > View > Table Fony and Row > "uncheck the check box" Show Icons > "OK"

Log in or join to reply