Resolving overallocation by calculation??
In the Open Standard
Yusuke KamuiMember for 18 years 5 months
- Created
- 1
- 4
0
Hi,
In the resource analysis of P5, there are multiple the fields being shown:
-Remaining Early Units
-Remaining Late Units
-Limit
-Cum Budgeted Units
-Cum Actual Units
-Overallocated Early Units
-Overallocated Late Units
Which among the fields above will I use to calculate manually the needed "Limit" (that is, how many more people I need to hire) per month to resolve all overallocation and overcome or compensate for the late units/work or uncompleted units/work from the past months??
I tried resource leveling but it will push out the schedule’s finish date by 2 years!!! So the only thing now is to increase manpower. But how to know how many more manpower we need per month? By using fields above and calculate it, right?
In the resource analysis of P5, there are multiple the fields being shown:
-Remaining Early Units
-Remaining Late Units
-Limit
-Cum Budgeted Units
-Cum Actual Units
-Overallocated Early Units
-Overallocated Late Units
Which among the fields above will I use to calculate manually the needed "Limit" (that is, how many more people I need to hire) per month to resolve all overallocation and overcome or compensate for the late units/work or uncompleted units/work from the past months??
I tried resource leveling but it will push out the schedule’s finish date by 2 years!!! So the only thing now is to increase manpower. But how to know how many more manpower we need per month? By using fields above and calculate it, right?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?