Forecast Manhours Calculation - Engineering Deliverable
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 11
- 4
0
Hello Everyone,
Can anyone explain how to calcualte the Forecast MAnhours for a Engineering Document/Delvierables. Say for Example
| Deliverable | Budgeted Manhours | Planned % | Actual % | Earned Manhours | Actual Manhours | Forecasted Manhours |
| A | B | C | D | E | F | |
| Tank Foundation Drawing | 100 | 35% | 5% | 5 | 12 | ? |
Regards
Jithin