Forecast Manhours Calculation - Engineering Deliverable

Jithin KambhikanamMember for 15 years 6 months
Created
11
4
0

Hello Everyone,

 

Can anyone explain how to calcualte the Forecast MAnhours for a Engineering Document/Delvierables. Say for Example

 

DeliverableBudgeted ManhoursPlanned %Actual %Earned ManhoursActual ManhoursForecasted Manhours
 ABCDEF
Tank Foundation Drawing10035%5%512?

 

Regards

Jithin

11 replies

Oldest first
  1. 0
    Bryc Ali ·

    Could you explain what you

    Could you explain what you are looking for ? if you want an analysis I can tell tou that you have a problem with you SV ans CV, because : SV= 5-35 = -30 and CV= 5-12= -7 you are late in time and cost budget.

  2. 0
    Zoltan Palffy ·

    if nothing changes the ratio

    if nothing changes the ratio is 12 to 5 meaning for every 12 hours that you spend you only earn 5 so at this rate the calculation would be 95 remaining budgeted hours. Therefore 95/5 =19 remainiing 5% increments to get to 100. That means 19X12 = 228 forecasted manhours remaining.

    another way to look at is is 95X12=1140 manhours / by 5 manhours that you earn is 228 manhours

    The total foreacted manhours would be 228 remaining plus 12 manhours already spent = 240 

    this is straight math 

  3. 0
    boozighalamoo ·

    hi I have got a question.in

    hi 

    I have got a question.in case of adding new document to document list,I need to asiign weight factors and it is gonna impact on total wight factor,can anyone clarify that is it correct to change the total weight factor after adding new docuemnts or I need to keep the total constant by using buffer?

  4. 0
    boozighalamoo ·

    hi I have got a question.in

    hi 

    I have got a question.in case of adding new document to document list,I need to asiign weight factors and it is gonna impact on total wight factor,can anyone clarify that is it correct to change the total weight factor after adding new docuemnts or I need to keep the total constant by using buffer?

  5. 0
    Jithin Kambhikanam ·

    Thanks Zoltan, So that is the

    Thanks Zoltan,

     

    So that is the use of Schedule Performance Index (SPI) ie Earned/ Actual = Budgeted / SPI.

     

    As posted posted by one of the other Person posted, if one more deliverable is added to the register how would you account the weightage for that.

    • Would be using the exisiting hours or
    • Or add new hours which increases the Total Manhours which would simultaneously decrease the weightage of all the other deliverable.

    Regards

    Jithin

  6. 0
    Zoltan Palffy ·

    if you add anything then the

    if you add anything then the total changes which means the number that you divide by increase and all numbers are reduced becasue there are now more elments that need to be divided by the total.

  7. 0
    Jithin Kambhikanam ·

    Ya Zoltan, Thats for

    Ya Zoltan, Thats for sure.

     

    Say a situation in which you were supposed to make 10 Drawings but the Dicipline Engineer thought that there is only 8 Drawings and gave the manhours for making the same say 80 Hours.

    But during execution he comes to know he needs to make 10 Drawings and adds the drawing. by then the Planning Engineer made a register which captures the progress of 8 Dawings and now this additional 2 drawings needs to be added. So in this situation the progress needs to be captured and its not a Change Order.

     

    So can you give us a idea of how to handle such a situation.

     

    Regards

    Jithin

  8. 0
    Zoltan Palffy ·

    right its still the ORIGINAL

    right its still the ORIGINAL SCOPE no chnage order

  9. 0
    Jithin Kambhikanam ·

    Hi Zoltan, So how to handle

    Hi Zoltan,

     

    So how to handle such a situation. 

    If it was already in the scope but was missed when calculating the weightage, but now you have to add it as it is part of Progress Measurement.

    So how can we do that ?

     

    Regards

    Jithin

  10. 0
    Anoon Iimos ·

    The problem is misconception.

    The problem is misconception. Firstly, your "forecast" is your budget or baseline and you don't change your budget in every update. Otherwise, your schedule will become endless or cannot be measured.
  11. 0
    Zoltan Palffy ·

    just add it and admit that it

    just add it and admit that it was missed 

Log in or join to reply