P6 Auto Refresh
In the Open Standard
Cristi ThorneMember for 18 years 8 months
- Created
- 1
- 2
0
In P6, my team is finding it very annoying that it periodically refreshes/saves. When you are tracing back logic, etc, and it refreshes and switches activities on you, it is frustrating.
Is there a way to change the settings so that it saves, but does not refresh? Is this caused by a user’s activity, or a built in save function?
It seems to happen at least every 30 mins.
Any help on this would be greatly appreciated.
cristi.thorne@shawgrp.com
Is there a way to change the settings so that it saves, but does not refresh? Is this caused by a user’s activity, or a built in save function?
It seems to happen at least every 30 mins.
Any help on this would be greatly appreciated.
cristi.thorne@shawgrp.com
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?