Change activity Id

Alka RevoMember for 19 years 4 months
Created
3
2
0
Hi,
I am using P6, my project has activity id as 7digits-3digits. I have just been told that SAP interface will take only 7digits-4digits.
Can anyone suggest how I can quickly add a digit to all my activity ids
Thanks
alka

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Alka,

    Try to use Global Change, choose from the following Parameter Values:

    Then Parameter Is Parameter Value Operator Parameter Value
    user_text7 = RightString(Activity ID,#)
    user_text7 = LeftString(Activity ID,#)
    user_text7 = SubString(Activity ID,#,#)
    And Activity ID = LeftString(Activity ID,#) & user_text7
    And Activity ID = LeftString(Activity ID,#) & user_text7
    And Activity ID = SubString(Activity ID,#,#) & user_text7

    Before doing this always create BACKUP COPY to your current project.


    Arnold
  2. 0
    Alka Revo ·
    Hi Arnold,
    Thanks a lot for helping.It doesn’t sound very bright, but I am not able to define user text here. Can you please help a bit more and explain a bit more how to do it. I have never used this type of paramaeter definition before.

    Kind regards
    alka
  3. 0
    Arnold Puy ·
    Hello Revo,

    Okey, can you please show me what you want to do. Say for example, you have an Activity ID = FJRA000010, then you want to change the first four letters to BLDG000010, all you have to do is to use Global Change using these Parameters:

    user_text7 = SubString(Activity ID,5,10)
    Activity ID = BLDG & user_text7

    Or you can use this:

    user_text7 = RightString(Activity ID,6)
    Activity ID = BLDG & user_text7

    And you can get the same result. However, before doing this always create BACKUP COPY to your current project. Just let me know and you can send it to me if ever you cannot do it. My e-mail address is p3-fer@sixco.ae I can do it for you.

    Regards,

    Arnold