P6 Scheduling problem ( need your help)
In the Open Standard
El GwapitoMember for 18 years 5 months
- Created
- 13
- 2
0
Dear all,
Im new in P6, by the way the proj is underway as of the moment but suddenly stopped by the month of July 01 -31 2008 & no progress at all, but when I updated & run the schedule(F9) by Aug.01,2008 WHY THE TOTAL PROJ PERCENTAGE COMPLETION(SAY BY DURATION) WAS TREMENDOUSLY INCREASING WITHOUT ANY PROGRESS AT ALL FROM THE PREVIOUS MONTH?Then I run again by sept 2008 still the total proj % completion is still increasing without any progress since July 2008?
How to resolved this conflict?
Help me out this PLEASE???
Im new in P6, by the way the proj is underway as of the moment but suddenly stopped by the month of July 01 -31 2008 & no progress at all, but when I updated & run the schedule(F9) by Aug.01,2008 WHY THE TOTAL PROJ PERCENTAGE COMPLETION(SAY BY DURATION) WAS TREMENDOUSLY INCREASING WITHOUT ANY PROGRESS AT ALL FROM THE PREVIOUS MONTH?Then I run again by sept 2008 still the total proj % completion is still increasing without any progress since July 2008?
How to resolved this conflict?
Help me out this PLEASE???
13 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?