This may seem a bit silly, but how much information do i need to include within a short term weekly Programme?

Thanks,

J

4 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi James

    Just do a time slice filter on your main programme from week before - current week - next week and your short term programee will appear.

    You may need to do sub filters for each work package.

    Best regards

    Mike Testro
  2. 0
    Smiling Shagger ·
    in nepal, probably theres no need of short term program, we solve any lookahead/recovery by everybody project participants sitting down together over a pot of bonk

    hempfully,
    smilingshagger cum global backpacker
  3. 0
    James Young ·
    How do i do a Time Slice Filter?

    Regards,

    James
  4. 0
    Mike Testro ·
    Hi James

    Start PowerProject Help

    Type in Time Slice and list topics

    Go to nr 9 on the list and follow the instructions.

    Best regards

    Mike Testro