Baseline in P5

Adekunle ArisilejoyeMember for 18 years 6 months
Created
1
2
0
hi,

pls whats the differnce btw a project baseline and a primary baseline in P5. which of the baselines does P5 use to measure progress against.

Cheers

Kunle

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hello,
    Project baseline can be seen by anybody allowed to see the project
    Primary and Secondary baselines are for the project owner (the planner) only
    That’s true if you are working in a multi-user environnement, with a planner and other users such as team members, managers, aso
    When you are using P5 as a standalone app, it makes no difference between project and primary baseline
    Alexandre