a warm greetings to all:

this regarding the issue on developing a programme.as what i have noticed i can link the activities in both bar chart and PERT.
can you please help ma which of this two methods is better?

and lastly,how can i project the concrete pouring schedule in the project lay out,this activity is not continuos everyday.is it possible to be put repeatedly in every part of the building structures?
sample:

Concrete pouring in raft foundation after 1 week
concrete pouring in core walls from B$ to grnd floor.

What i mean which is the best way for me to put the concrete pouring activity while this is not continuous everyday.

your help is highly appreciated.

regards,
bon


5 replies

Oldest first
  1. 0
    Charleston-Joseph Orbe ·
    Bon,

    You need to establish WBS at sufficient level to place common activity pour concrete.

    Please review the idea behind WBS

    Regards,
    Charlie
  2. 0
    Urbicio Bon Yrabono ·
    hi mr. charlie,

    thanks for your help. i will do it.

    regards,

    bon
  3. 0
    Anoon Iimos ·
    there is no problem if you repeat the same activities a thousand times, in construction, it is the only way, i suggest you use activity codes (more flexible)

    For example:

    1.layout
    2.formworks
    3.rebars
    4.quality inspection
    5.place/pour concrete
    6.strip formworks

    you can repeat the same group of activities (above)for all the concrete structures that you may have.

    once you have established your codings, then it’s easy to apply filters, so that you will only show "pour concrete" to occur on certain dates.

    hth
  4. 0
    Urbicio Bon Yrabono ·
    hi anoon,

    thanks for the information you’ve given.

    regards,

    bon
  5. 0
    Shahzad Sikandar ·
    yest thats right

    call them Pour 1, pour 2 and so on,
    code them if you want to see them in different areas but under one header i-e Concrete Pour (once all pour activities are coded against activity code (concrete pour)

    you could also do resource linking or concrete supply linking.

    hope this helps

    cheers