Good Monig. Mr Rodel

I have an activity 10 days duration max.working Hr 10/d

This activity having four resources 2 nonlabour and 2 labour,


activity name is Foundation, OD 10 days. ( cal 6D/week)
Resource , 1 Execavator Nonlabour.
2. Execavator Operator (labour)
3. Roller Operator (labour)
4. Roller (nonlabour)
first 5 days for excavation, and last five days for Rolling,

i assing these resourece to avtivity all resource are over alocating,

Please advise me how i can assign these resource to activity avoid the resource over allocating.

How many units i have to allot for each resource.

Thanks & Regards


3 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Shazia

    Split the task into two distinct activities.

    1 bar for digging - 1 bar for rolling.

    It is not good planning to have multi task activities.

    Best regards

    Mike Testro
  2. 0
    Trevor Rabey ·
    As Mike says, this is obviously 2 tasks.
    Also, if your equipment has an hourly or daily cost and a calendar, then it is really just like a labour resource.
  3. 0
    Shazia khan ·
    Dear Sirs

    Thanks for your reply.

    I have broken down in to two Task.

    Regards
    Shah.