Interruptible vs. contiguous

Moutassem Al KouatliMember for 19 years 1 month
Created
2
4
0
Dear Planners,

can anybody advise whene to use interruptible or contiguous schedule duration while scheduling a program,
not from the software point of view (which i know)
but from a practical point of view, i mean in order to be as close as possible from what happens in reality, and which one is better, and what the effects of each one?

thanks and regards

2 replies

Oldest first
  1. 0
    Anoon Iimos ·
    i guess it’s like progress override or retained logic

    (i’m just a trying hard aspiring planner by the way)
  2. 0
    Samer Zawaydeh ·
    Hi,

    Your activities should be connected to the resources. So if you have material deliveries coming in with certain frequency and the rate of completion at site is higher than the rate of supply to site you will have interrupted duration; that is once the material comes to site you can complete the activity.

    Again, if you have a special person doing a certain job like commissioning of a system, then when this person at site, this activity can be ongoing.

    On the other hand, excavation, concreting, steel reinforcement, block building, plastering, and most of the civil works are continuous activities.

    Good luck,

    Samer

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?