Float usage and Baseline
In the Open Standard
Rajeev P.U.Member for 18 years 11 months
- Created
- 10
- 3
0
Situation 2:
It is not defined anywhere in the contract documents for whom and by what percentage the float is to be shared by Engineer and contractor.
Contractor is planning to use the float of certain activities to insert some additional activities (due to change in methodology) in the consented base line program to avoid having any impact on the project completion date. As PMC (Engineer) we pointed out that the float have to be shared on 50-50 basis and further the program to be reviewed by Engineer prior to use it as a baseline.
1. Is it allowed to insert additional activities in a consented baseline program and use the same as baseline program OR better consent it as a Revised Baseline Program (The contractor argument is that since it doesn’t have any impact on critical path there is no need to consent as a Revised Baseline Program).
2.How the float will be distributed among PMC (Engineer) and Contractor since it is not defined anywhere?
It is not defined anywhere in the contract documents for whom and by what percentage the float is to be shared by Engineer and contractor.
Contractor is planning to use the float of certain activities to insert some additional activities (due to change in methodology) in the consented base line program to avoid having any impact on the project completion date. As PMC (Engineer) we pointed out that the float have to be shared on 50-50 basis and further the program to be reviewed by Engineer prior to use it as a baseline.
1. Is it allowed to insert additional activities in a consented baseline program and use the same as baseline program OR better consent it as a Revised Baseline Program (The contractor argument is that since it doesn’t have any impact on critical path there is no need to consent as a Revised Baseline Program).
2.How the float will be distributed among PMC (Engineer) and Contractor since it is not defined anywhere?
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?