Impact check
In the Open Standard
Rajeev P.U.Member for 18 years 11 months
- Created
- 0
- 3
0
Situation 3:
In an updated program when we ask for the reason of overall delay of 2 months;
Contractor version - equipment delay is having more impact
PMC version - concurrent delay - but structure delay is dominant.
In order to check the equipment activity was updated with 100% (case 1: with original program start & finish date) and (case 2: with the cut off date as the finish date, start date=cut off date-OD).In both the cases the structural delays remain same.
When we do such excercise to check which activity(s) is having major impact on other, what date is to be considered for the particular activity (here eqpt){whether the planned dates or the cut off date as finish date} as the other activities in the program are updated as of cut off date.
Rajeev
In an updated program when we ask for the reason of overall delay of 2 months;
Contractor version - equipment delay is having more impact
PMC version - concurrent delay - but structure delay is dominant.
In order to check the equipment activity was updated with 100% (case 1: with original program start & finish date) and (case 2: with the cut off date as the finish date, start date=cut off date-OD).In both the cases the structural delays remain same.
When we do such excercise to check which activity(s) is having major impact on other, what date is to be considered for the particular activity (here eqpt){whether the planned dates or the cut off date as finish date} as the other activities in the program are updated as of cut off date.
Rajeev
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?