How to forecast construction manpower ?
In the Open Standard
Jinsong LuoMember for 17 years 11 months
- Created
- 2
- 4
0
Does anyone know how to forecast the direct manpower at the very beginning of detail design?
Under following circumstance;
1. Basic Design completed.
2. Detail design not completed, we have no accurate MTOs.
3. Chemical plant
I just know there are about 300 pcs equipments, 14 areas or units, including 1 MCC room, 1 cooling tower, 1 production building with 9 floors and 50 meters high, 1 piperack about 200 meters long, others are tank farms(about 15 site prefabrication tanks) and accessory buildings .
Can any one give me some idears?
Under following circumstance;
1. Basic Design completed.
2. Detail design not completed, we have no accurate MTOs.
3. Chemical plant
I just know there are about 300 pcs equipments, 14 areas or units, including 1 MCC room, 1 cooling tower, 1 production building with 9 floors and 50 meters high, 1 piperack about 200 meters long, others are tank farms(about 15 site prefabrication tanks) and accessory buildings .
Can any one give me some idears?
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?