Skip to content

P6 Steps

Joel ClarkMember for 17 years 10 months
Created
3
2
0
I haved added steps to my activities. I have updated with a percent complete. I see nothing changing in the physical percent complete. Am I missing a setting? Why will it not calculate the new percent complete?

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Joel,

    Go to Project Detail--> Calculations, mark the checkbox next to "Activity percent complete based on activity steps"

    HTH.

    Arnold
  2. 0
    Joel Clark ·
    Got it! Thanks Arnold. You Da man!
  3. 0
    Arnold Puy ·

    You are welcome Joel..

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?