Resource and Cost Planning Steps

Mon MelendresMember for 15 years 3 months
Created
8
3
0

To All:

hello people. i am just registered to this awesome site. maybe it's been discussed here many times but pardon me i'm just new to this site.

will somebody guide me how to have steps on resource and cost allocation? or where i will go from here?

thanks in advance. more power to you people.

mon

8 replies

Oldest first
  1. 0
    Anoon Iimos ·

    you can start from the BOQ,

    you can start from the BOQ, if its not available then you can develop one, by reading and studying drawings, specifications, etc.

    next step is how you are going to build your project?; you may have lots of options considering resources to be used like equipment (automation) and manpower (skills may differ).

    costs will also vary, depending on locations, quality of materials specified, manpower skills; period or time of construction; method of deliveries, etc.

  2. 0
    Mon Melendres ·

    Thanks Anoonit's a great hint

    Thanks Anoon

    it's a great hint considering that i'm a newbie in planning.

    hope you don't mind follow up questions...

    is the curve in resource profile (i.e. curve of the total resources) equal to the s-curve itself?

    is it advisable to minimize the kinds of resources? say if i have already EXACAVATOR (Hammer & Bucket) on list of resources, I will not put JCB anymore on the list?

    Thanks again Sir for your time....

  3. 0
    Anoon Iimos ·

    sorry, i'm not sure if I

    sorry, i'm not sure if I understand what you were asking; resources and costs cannot be defined in s-curve

    s-curve is dependent on the units used, and it can be anything measurable

  4. 0
    Mike Testro ·

    Hi Mon I prefer to keep

    Hi Mon

    I prefer to keep things simple.

    When modelling task durations in a construction project I use one resource called hours which is extracted from the BOQ/Cost plan.

    This is balanced by the gang size.

    Costs are put in at summery level 3 and 2

    Best regards

    Mike Testro

  5. 0
    Mon Melendres ·

    Thanks a lot Mike.Though it's

    Thanks a lot Mike.

    Though it's still a bit tough, hope I'll understand this sooner.

  6. 0
    Mon Melendres ·

    Thanks a lot Mike.Though it's

    Thanks a lot Mike.

    Though it's still a bit tough, hope I'll understand this sooner.

  7. 0
    Mon Melendres ·

    Anoon:Sir I am using P3, I

    Anoon:

    Sir I am using P3, I already input all the resources. When on the main window of P3, the curve I am talking is the curve generated at command ''ctrl + f7''. Coz it looks like the same on the s-curve i generated on graphic report.

    Anyway thanks again for your time.

  8. 0
    Mon Melendres ·

    Anoon:Sir I am using P3, I

    Anoon:

    Sir I am using P3, I already input all the resources. When on the main window of P3, the curve I am talking is the curve generated at command ''ctrl + f7''. Coz it looks like the same on the s-curve i generated on graphic report.

    Anyway thanks again for your time.