Exporting/Importing Projects

Catherine BarthelemyMember for 18 years 4 months
Created
3
2
0
Would anyone be able to tell me if you can import/export a project without showing the resources. This being for commercial reasons...
Anyone?

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Catherine,

    If you want to export a project into .xer file without any resources, all you have to do is to make a copy of the project you wanted to export. while pasting it into new project, In "Copy Activity Option" dialog box remove the check next to "Resource & Role Assignments" then OK.

    Export the newly copied project without any resources in it.

    You can import project without the resources by creating new Update Project Options then modify. Under "Data Type: Global" for Resource Codes, Values, Roles & Resources select "Do Not Import". Make sure that the one you created make use as a default.

    HTH.

    Arnold
  2. 0
    Catherine Barthelemy ·
    Arnold,


    Just tried and it’s just what I needed!! Simple solution really, once you’ve thought of it that is...!
    Thank you very much for your time!

    Catherine
  3. 0
    Arnold Puy ·

    You are WELCOME..