How filter out all successor

Mch 714Member for 18 years 6 months
Created
3
3
0
would you give me a select method. how filter out all successor for an activity by relationships. (no longest Path)

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi mch 714,

    Try this:

    (All of the following)
    Where Longest Path "equals" No
    And Successors "is not equal" Blank

    Note:
    Blank means: you don’t need to put any value. Just leave it blank.

    HTH.

    Arnold
  2. 0
    Mch 714 ·
    Thanks for your guide. but I can’t find Successos in Select criteria. Filter out successors of any activities have relationships for an special activity.
  3. 0
    Ali Farhat ·
    Schedule using "multiple float paths"
    and then group your activities according to the float path
    the group that includes your activity will show you the successor, the successor of the successor etc...
    hope that this is what you are looking for