Generating S-Curve and Histogram

Ese OsoroMember for 18 years 7 months
Created
1
4
0
Hi All,
I did carry out steps to generate S-Curve but seems not to work. While carrying out the steps , there seems to be no histogram on the activity usage profile. Do i have to generate the histogram first before applying the steps to generate the S-Curve. let me know hwo to generate the histogram.
Thanks for the urgent assistance
Regards
Ese

1 reply

Oldest first
  1. 0
    Ali Farhat ·
    I dont know what are the steps you followed but please consider the following notes:
    right click on the graph in the right bottom corner -> activity usage profile options, data tab:
    -show bars/curves -> check the box under "by date" for histogram, and under "cumulative" for curves

    -choose the "costs" in the display section

    -make sure the to choose the total in the "filter for bars" section

    if still not working, please tell me what steps are you following.
    regards,