S-curve
In the Open Standard
RK
Ritesh KumarMember for 20 years 6 months
- Created
- 12
- 2
0
12 replies
Oldest first- 0ZHZhang Haixiang ·Hello,
the so called ’s-curve’ is a kind of line chart. e.g. cost along timescale.
a lot of software can draw this kind of chart. the most popular one may be MS Excel.
the problem is from where you get the data.
for scheduling, most of the planning software can generate the data, they also have the ability to draw the curve.
I suggest to find a appropriate software for your planning work rather than a software for s-curve.(for the curve excel is enough) - 0PJPhilip Jonker ·Hi Paul/Ritesh,
I am not an expert on P (e) 3.5, but what Ritesh needs to find out is how to export to excel, and then he has to set up the s-curves there. If you can do this with hyperlinks, please explain. It can be done in newer versions, via other software, but if Paul has a trick up his sleeve, let us know about it. Paul thanks for gettting my braincells working here, will try this trick tomorrow, and let you guys know if I have any success.
regards - 0PAPierre Azar ·Dear Ritesh
if you’re using P3 version 3.1 then when you allocate resources to the activities, say manhours, primavera will automatically produce S-Curve for you. just go to tools, graphic reports, resource and costs. if you need further clarifications don’t hesitate to request it.
smile - 0PJPhilip Jonker ·Hi guys,
Give the guy some help, he is working on one of the P3e versions, and needs a report to generate the information. Once he has generated the the report, he then has a choice how to use it. The best way is probably excel. I know how to do it in PM v5 and P3, the question is how is is it done in P3e v3.5 and I will try to find out, as I have a guy working for me who knows all the versions, and can help. The point is if you do not have the correct answer, try not to confuse people anymore. Suggestions are OK as we all learn from them, but try and stay within the subject matter. - 0PPPrashant Patel ·Copy Paste data from Primavera to Excel.
Then put formula to distribute weitages whithin range of duration Early Start & Early Finish same for late dates.
u will get the early & late S - Curve.
( if u want formula give yr mail add to me)
Same u can also do in Primavera by doing non labor resourse loading in Primavera p3 e/c and generate S - Curve in primavera it self.