Deleting activity codes from P5/P6
In the Open Standard
Khaled CharkieMember for 17 years 10 months
- Created
- 1
- 19
0
We are a group of planners working on many projects. We use activity codes, and by time we have created many activity codes. Some of them haven’t been used at all. And now we want to delete the unused activity codes. Any suggestion of how to filter the activity codes that aren’t used in any project and then delete them?
Thanks
Thanks
1 reply