Cathodic protection groundbed scheduel

Katalin HovanyiMember for 23 years 6 months
Created
1
2
0
I need to estimate the manhour and duration for approximately 50 m deep 8" diameter groundbed.
I guessed:
2 days transport&drilling&piping 48 hours
3 days anod&backfilling&abouve ground installations 72 hours
Is it more or less correct or I need to calculete with different parameters? I hope somebody scheduled something similar and can give me some actual data.
Thanks
Katalin

1 reply

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Katalin,

    I would suggest that you contact a master driller in your company if you are on the Contractor side or your local soil investigation company if you are on the Owner side.

    My guess is that the numbers that you are proposing are on the optimistic side.

    Best Regards,

    Samer