Cathodic protection groundbed scheduel
In the Open Standard
Katalin HovanyiMember for 23 years 6 months
- Created
- 1
- 2
0
I need to estimate the manhour and duration for approximately 50 m deep 8" diameter groundbed.
I guessed:
2 days transport&drilling&piping 48 hours
3 days anod&backfilling&abouve ground installations 72 hours
Is it more or less correct or I need to calculete with different parameters? I hope somebody scheduled something similar and can give me some actual data.
Thanks
Katalin
I guessed:
2 days transport&drilling&piping 48 hours
3 days anod&backfilling&abouve ground installations 72 hours
Is it more or less correct or I need to calculete with different parameters? I hope somebody scheduled something similar and can give me some actual data.
Thanks
Katalin
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?