Skip to content

Ship impact protection system

Sunil BabuMember for 15 years 11 months
Created
2
3
0

Dear all,

   I need some guidelines for doing a ship impact protection system project programme. The major

   activities includes construction of two berths and a fender system for the ship impact protection.

   What are the major concerns while planning a programme for this work, berth construction  includes

   piling works also.  Expecting your valuable view points,

   With Regards,

           Sunil.

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Sunil Piling will probably

    Hi Sunil

    Piling will probably be done from an ofshore barge.

    If so then you have to consider:

    State of the tide

    Wave configuration

    Weather - monsoon

    Support and supply tenders

    When piling is in progress the rest of the work can follow for the jetty deck and top beams.

    After that you will have normal access.

    Best regards

    Mike Testro

  2. 0
    Sunil Babu ·

    Hi Mike,Thanks a lot for your

    Hi Mike,

    Thanks a lot for your valuable reply. In case of SIPS piling method what productivity

    rate are we following? ,Thanks in advance for your reply..

    Best Regards,

    Sunil.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?