Suretrack

Ferdinand AnchetaMember for 18 years 11 months
Created
2
2
0
If i want to update an activity regarding Percent Complete, can i update at one time only? Say i want to change the Percent complete in the activity form. Does the updating in the activity form will also update the Cost and Resource form as well? Please advise.

2 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Ferdinand,

    If your program is linked together correctly, then it should work, yes.

    Best,

    Samer
  2. 0
    Ferdinand Ancheta ·
    Samer,

    Thanks for the reply. However, am not sure if you referring Percent Expended wherein the percentage of actual cost which has been spent to date. And Percent Complete is the percentage of the activity which is complete. Thus, my query refers to the automatic updating of the percent complete both for the activity and cost form. Unless otherwise let Suretrack to calculate the Percent complete. But my program is applied on a manual updating coz’ i’m controlling the completion dates of each activity based from the availability of our resources and milestones.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?