Any of you clever people know how to stagger an activity with non working periods in between over a stretched amount of time and showing as "staggered" bars on one line on the gant chart. (ie: 1 day re-occurring meeting very month)

2 replies

Oldest first
  1. 0
    Nigel Winkley ·
    Try creating a special calendar set to one day per month and assigning to that activity, then tick the Neck Bars for Non-Work periods.
    Nige
  2. 0
    Catherine Barthelemy ·
    thank you very much Nigel I shall try that.
    oh the fun we have!