Statistical data

Luca MasinaMember for 17 years 8 months
Created
4
2
0
Hi everybody, I would like to have some information regarding petrochemical plant:
Have someone got statistical data concerning timetable for welding of piping and fittings, detailed for material, size, rating and type of welding?

Thank in advance.

Regards

4 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Luca,

    Did you check the American Welding Society?

    Or you can check the major welding companies like Lincoln and Esab. I am sure that they will have everything you want. It is a small call to your local supplier of welding materials. Definitely the manuals exist for a long time.

    Best Regards,

    Samer
  2. 0
    Luca Masina ·
    Samer, thanks so much for your suggestion.

    best regards
    Luca
  3. 0
    Hady Mohamed ·
    Luca,

    Whilst allocating the durations for the welding activities, do not forget to allocate enough time for the "Fit-Up" phase the precedes the actual welding. That is, the edge preparation of both sides of the butt-weld, a tack weld in place, and an inspection by the QC Inspector of the quality of the Fit-Up process.

    From my (limited) experience, the duration of the Fit-Up process can be overlooked and this may lead to inaccurate schedules.
  4. 0
    Samer Zawaydeh ·
    Dear Friends,

    The Fabrication process time depends on the item being fabricated.

    Structural Steel is usually divided into four sections;
    Light steel
    Medium steel
    Heavy steel
    Extra Heavy steel

    The manhours spent in production (complete item) usually depends on the weight of the item in case it is just structural steel.

    The range can be from 9hours/MT - 100+hours/MT depending on the type of structure and the availability of required equipment.

    Best Regards,

    SAmer