1 Project - 2 Contractor - Import of Data
- Created
- 5
- 3
Hello Everyone,
May be this topic has been dicussed here but couldnt find it.
The situation is I am the Client Planning Engineer for a "Building Project". I have 2 Subcontractors Civil Contractor and MEP Contractor and they have prepared the baseline schedule.
So I need to update my schedule which is a combination of Civil and MEP Works. So I want to import data from Civil Contractors updated scheule as well as MEP Contractors updated schedule.
At the end I have one updated schedule which shows both Civil and MEP Work.
How Is this done ?
Any link or a pictorial represntation on how to do that would be really helpful.
Regards
Jithin
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?