Skip to content

WBS for a Substation

Hady MohamedMember for 20 years 9 months
Created
7
60
0
I am trying to acquire more information on Electrical Substation Planning.

I would be grateful if any planer with an Electrical Engineering background can help with suggesting a WBS for designing and building an Air-Insulated-Substation.

I would presume that the first 2 levels would be as follows :

SS.1 Design Phase
SS.2 Procurement
SS.3 Civil Works for Substation Building
SS.4 Installation Works
SS.5 Testing & Commissioning

Electrical Engineering is not my specialty, and I was not assigned to create a schedule. I’m only trying to learn more about the subject.

Regards

7 replies

Oldest first
  1. 0
    Anoon Iimos ·
    The construction of a concrete substation is like any other concrete building but you need lots of block-outs. If it is air-insulated, then you have air-conditioning system.
  2. 0
    Mike Testro ·
    Hi Adi

    Just make sure that you can get the kit into the building before you seal it up.

    Best regards

    Mike Testro
  3. 0
    Shaiju Thomas ·
    Hi Hady,

    Installation works in the substation can be broken into following;

    1. Installation

    1.1. MEP works inside substation
    1.2. Installation of substation equipments (transformers, MDSs etc)
    1.3.Power Cable Installation
    1.4.Bus duct installation
    1.5.Control Cables installation
    1.6.Cable terminations.

    2. Testing activities

    2.1.Transformers and Panels dry check
    2.2.Cable testing
    2.3.Transformers and Panels testing (protection tests)
    2.4.System sequence tests
    2.5.Cable HIPOT tests
    2.6.Authority Inspection and witness tests
    2.7.Final commissioning and Power On

    Hope this will help
  4. 0
    Pacifico Pallasigui ·
    Planners,


    I am preparing a schedule for an 2 nos. of electrical substation here in Saudi Arabia with area = 6000 m2 . Around how many months is the duration of this partion?

    Thank You

    Pacifico
  5. 0
    Samer Zawaydeh ·
    Dear Pacifico,

    It depends on the location and the environmental factors. Say you need 3-6 months for procurement of equipment, and during that time you can get the Civil Structures up.

    Say 9-12 months as as starter.

    With kind regards,

    Samer
  6. 0
    Shah. HB ·
    Hi Pacifico

    Check the long lead material procurement duration with your project team because in substation you will find many equipment on approval of submittal they will undergo factory acceptance test which consumes some duration in some case it is critical
  7. 0
    Pacifico Pallasigui ·
    Shahul,

    Thank you very much, but im preparing only the construction part of the substation like Civil, MEP and Finishing work without the procurement activities. I’ll just want to know the more or less the duration for Civil, MEP and Finishing for a 6,000 m2 substation.

    Thank You
    Pacifico

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?