Activity Code

Roger AssiMember for 20 years
Created
4
2
0
HI,

IF I CREATE AN ACTIVITY CODE BY CHOOSING ’PROJECT’,HOW CAN I TRANSFER THIS LEVEL OF ACTIVITY CODES TO ANOTHER PROJECT.
NB: WHEN I CHOOSE MAKE GLOBAL,IT IS DELETED ALL THE ACTIVITY OF THE PROJECT ITSELF.
YOUR COOPERATION IS HIGHLY APPRECIATED.

THANKS

4 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Roger

    In powerproject you can copy / paste anything between projects.

    Best regards

    Mike Testro

    ps try not to use block capitals - it seems as though you are shouting at us - Charleston got into a big argument on this subject.
  2. 0
    Roger Assi ·
    THANKS MIKE .

    HAVE A NICE DAY
  3. 0
    Arnold Puy ·
    Hi Roger,

    The other workaround on how to transfer or copy the Activity Codes by copying the project and in the "Copy Project Options" remove the check next to Activities.

    Or you can use the SDK and Parser & Builder from Primavera Knowledgebase.

    Arnold
  4. 0
    Arnold Puy ·
    Hi Roger,

    Okey, here is the best way to do. Open the two projects. The project defined with activity codes and the other one project without the activity codes.

    Go to Enterprise --> Activity Codes, Project radio button and select modify. Now, select all activity codes you want to copy & right click paste it to EPS/Project:

    Regards,

    Arnold

Log in or join to reply