Assigning Non labor resources inquiry

George RidulmeMember for 18 years 4 months
Created
1
2
0
Hi guyz,

I am having difficulty in terms of assigning non labor resources.
The problem is when I assign a nonlabor, let say a crane at 10hrs/day (budgeted units/time)on the resources for a certain activity, once i opened the resourced usage profile, it doesnt reflect a 10hrs/day, (usually it reflects more than what i have assigned on the resource). Thus, if i have only 10hrs working time/day, the crane reflects an overallocation.

Do i miss something here,


Thanks in advance,

George

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi George,

    Before assigning the Nonlabor Resources, try to change the Default Units/Time equals to 10/d then assign it to corresponding activities.

    Try to use "Fixed Duration and Units/Time" as Duration Type. The only thing is, your Budgeted Units will change.

    HTH.

    Arnold