Assigning Non labor resources inquiry
In the Open Standard
George RidulmeMember for 18 years 4 months
- Created
- 1
- 2
0
Hi guyz,
I am having difficulty in terms of assigning non labor resources.
The problem is when I assign a nonlabor, let say a crane at 10hrs/day (budgeted units/time)on the resources for a certain activity, once i opened the resourced usage profile, it doesnt reflect a 10hrs/day, (usually it reflects more than what i have assigned on the resource). Thus, if i have only 10hrs working time/day, the crane reflects an overallocation.
Do i miss something here,
Thanks in advance,
George
I am having difficulty in terms of assigning non labor resources.
The problem is when I assign a nonlabor, let say a crane at 10hrs/day (budgeted units/time)on the resources for a certain activity, once i opened the resourced usage profile, it doesnt reflect a 10hrs/day, (usually it reflects more than what i have assigned on the resource). Thus, if i have only 10hrs working time/day, the crane reflects an overallocation.
Do i miss something here,
Thanks in advance,
George
1 reply
Oldest firstLog in or join to reply