Infrastructure Project Productivity Rate
- Created
- 18
- 6
18 replies
Oldest first- 0SZSamer Zawaydeh ·Dear Chris,
It depends on the type of soil layers and the equipment that you are using. It is a broad range. I would recommend that you read the soil reports and discuss with your construction team the type of equipment that they are considering.
Subsequently, you can download the charts from the website of the equipment companies and factor in the skilled operators expected productivity.
With kind regards,
Samer - 0JBJames bid ·Thanks Raviraj!
Actually , It is underpass and Bridge.
I want to know the excavation rate for all the equipments that will be used, Manpower to be used including steel fixers, masons , carpenters.
If you have can you email me in (please contact christopher by the private message service.)
Many Thanks - 0JBJames bid ·Thanks Samer!
Can you share it to me the websites so that i can download all the Productivity rates
How about the manpowers? as what i asked to Raviraj? do you have standard productivity rate? Can you share it to me also?
I know you are now " high Caliber" in planning because of your experience.
I hope you could help me.
Thanks - 0MTMike Testro ·Hi Christopher
Excavation output is not determined by the rate of excavation - you can find the listed performance ratings on any manufacturers website.
You have to calculate the haul & disposal rate for the excavated material.
This is a formula based on:
Haul distance
Paylod of haul equipment
Load and tip time
Haul speed KMH
When you have calculated the haul time you can balance the excavation rate by the number of haul units.
Aim to have enough units so that the excavator is working at about 80% capacity.
Best regards
Mike Testro
PS I am moving this thread to the planning discussion section. - 0RDRafael Davila ·Mike,
Your postings about earthwork production rates are the correct way to estimate excavation output. It is not as simple as a single number as posted under PP Rates. PP Rates can be misleading as they miss a big part of the picture. Not only earthwork is interesting but formwork using several methods, especially if unconventional such as slip forming.
Discussion of production rates is a much needed title, we should raise the bar.
I would suggest that when you click at Rates this would get you to a forum for this purposes, where everyone would post production rates and the logic behind it in appropriate threads. It will also relieve some burden on PP Admin.
Best regards,
Rafael - 0MTMike Testro ·Hi Rafael
I do not use production rates for resource modelling.
Even if I wanted to I could not access the PP rates section because I have not introduced enough members.
I extract the resource hours from the cost plan / BOQ and use the total hours to allocate to the tasks.
Best regards
Mike Testro - 0SZSamer Zawaydeh ·Dear Christopher,
I would recommend that you google the following:
Caterpillar Production Rates
In addition to the good replies thus far, you can get also the following
www.contractor-books.com/Cr/National_Earthwork_Estimator.htm
Hope that the information helps.
With kind regards,
Samer - 0ATAlex Thompson ·
Caterpillar, the biggest
Caterpillar, the biggest heavy equipment manufacturer and 4th-largest exporter on the globe, reported record profits Friday. I read more information here: Caterpillar records record $1.22 billion profit for Q1 2011.
Figures point to a $1.22 billion profit, 426 % higher than First quarter last year. Sales increased 57 % to $12.95 billion over the same period. Caterpillar managed to stay in business amidst recession. Cheers!
- 0MAMohammed Amjad Ghaniwala ·
jeff, i appreciate your help.
jeff,
i appreciate your help. can you please email to me also....
my email address is amjad.ghaniwala@gmail.com
thanks,
mohammed amjad
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?